Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 4
Secondary Department Head/Elected Official: Lesley Briones
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 24208MF3JV01
Vendor/Entity Legal Name (if applicable): Resalire Infrastructure Solutions
MWBE Contracted Goal (if applicable): 21.415%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with Resalire Infrastructure Solutions, LLC to add language to Exhibit A-1 (SOW) for developing a comprehensive Emergency Response Plan for Precinct 4 to cover all possible natural disasters, UPIN 24208MF3JV01, Precinct 4, MWBE Contracted Goal: 21.415%.
end
Background and Discussion:
There have been several natural disasters that effected Harris County during the past years. An Emergency Response Plan is critical to develop Standard Operating Procedures (SOP) to streamline and improve efficiency in emergency response process. The proposed plan will develop SOPs, disaster response team structure, site plans at each Precinct 4 community center for food and water distribution and debris disposal sites and site plans.
Expected Impact: The Emergency Response Plan will enable County staff to be better prepared for the 2025 Hurricane season along with any other future natural disasters such as hard freezes, tornados, derechos, etc. This will make recovery efforts more efficient and improve resiliency.
Alternative Options: If consultant assistance is not available, County staff will have to develop the plan.
Alignment wi...