Primary Department: Toll Road Authority
Primary Department Head/Elected Official: Roberto Trevi?o, P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Proposals/Bids
Project ID (if applicable): 25/0164
Vendor/Entity Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): 17.75%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to advertise for construction bids for the removal and replacement of traffic signal equipment and related improvements at Canino Rd and West Hardy Toll Road, as part of Barrier-Free HCTRA Program (Precinct 2, MWBE Contracted Goal: 17.75%).
end
Background and Discussion:
The proposed project is located along Hardy Toll Road at the intersection of Canino Rd. and Hardy St. It connects residents across the Hardy Toll Road, by providing safe and ADA accessible connections that use the existing bridge spanning across the tollway. The proposed improvements, replacing a traffic signal and adding a HAWK beacon at the intersections, will improve safety along the corridor by bringing the intersection to current design standards. The project aligns HCTRA and Harris County's goal to improve safety and accessibility along HCTRA facilities for all Harris County residents.
Expected Impact:
This project aligns with Harris County's goals of providing a reliable, safe, sustainable, and evolving mobility system that meets the diverse connectivity needs of all Harris County residents. Funding from this project comes from Toll Road Authority.
Alternative Options:
No other recommended solution for this identified need.
County Strategic Plan Goal: 2. Co...