Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official:
Regular or Supplemental RCA: Regular RCA
Type of Request: Report
Project ID (if applicable): 23102MF2US01
Vendor/Entity Legal Name (if applicable): Agha Engineering LLC
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request for approval of a study report prepared by Agha Engineering LLC for Sweetwater Lane from West Mount Houston to West Canino Road, Precinct 2, UPIN 23102MF2US01.
end
Background and Discussion:
The project is in north Harris County in the Aldine area, Precinct 2. Agha Engineering LLC was awarded a contract to provide roadway reconstruction and related improvements along Sweetwater Lane from West Mount Houston to West Canino Road. Based on that agreement, Agha Engineering has submitted the final study report on June 05, 2025.
Expected Impact:
The project will reconstruct the existing asphalt pavement and provide a 27-feet wide typical concrete pavement section from face of curb to face of curb, centered in the existing right-of-way with 6-feetwide sidewalks and ADA ramps on either side, including widening the bridge over Halls Bayou to accommodate the proposed sidewalks. The design proposes to replace the existing open ditches with an underground storm sewer system with inlets and lower the existing pavement pro?le to capture storm water from outside of the right-of-way.
The design considered roadway geometry requirements and constraints, detention and mitigation recommendations, environmental constraints, tra?c control construction phasing re...