Primary Department: Purchasing
Primary Department Head/Elected Official: Paige McInnis
Secondary Department: Toll Road Authority
Secondary Department Head/Elected Official: Roberto Trevino
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Renewal
Project ID (if applicable): 240038
Vendor/Entity Legal Name (if applicable): Professional Traffic Control, LLC
MWBE Contracted Goal (if applicable): 9.9%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request for approval of a renewal option with Professional Traffic Control, LLC for pavement markers, markings and related items for the Toll Road Authority through June 3, 2026, at a cost of $783,000, and for the County Clerk to execute any applicable bonds to be received (240038), MWBE Contracted Goal: 9.9%, MWBE Current Participation: 100%.
end
Background and Discussion:
Request for approval of the first renewal option with Professional Traffic Control LLC for pavement markers, markings and related items for the Toll Road Authority, at a cost of $783,000, subject to applicable bonds to be received (24/0038).
Expected Impact:
The approval of this renewal allows HCTRA to continue to receive services for pavement markers, markings and related items as needed throughout the system
Alternative Options:
No other recommended option for this identified need.
County Strategic Plan Goal: 1. Make Harris County safer and more just.
County Strategic Plan Objective: F: Ensure safety and security for all using the county's transportation network in alignment with the County's Vision Zero plan.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): F1: Strengthen the County's commitment to Vision Zero principles a...
Click here for full text