Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0141, UPIN 23101MF2P901
Vendor/Entity Legal Name (if applicable): Wilson Building Services, Inc.
MWBE Contracted Goal (if applicable): 32%
MWBE Current Participation (if applicable): 92.47%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Wilson Building Services, Inc., in connection with final construction of George Floyd Memorial at Tom Bass Park Ph 2 - 2022, adding 130 calendar days, with an addition in the amount of $19,912.56, Job No. 23/0141-1, UPIN 23101MF2P901, Precinct 1, MWBE Contracted Goal: 32%, MWBE Current Participation: 92.47%.
end
Background and Discussion:
This project is to expand the memorial plaza for George Floyd statue monument, which includes developing trails that connect the community center, parking lots, pavilion and existing trails to the George Floyd Memorial located in Precinct 1's Tom Bass Park III.
Changes include the reconciliation of final numbers for the project, the addition of new lines items to complete the project such as additional time, culvert for drainage, grading of ditches, removing existing concrete and removal of an existing culvert.
Expected Impact:
Changes will allow for the project to be constructed per the original intent.
Alternative Options:
Leave out additional scope and complete work using other county resources.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, an...