Title: Request for approval of a change in contract with McCory Engineering in connection with the construction of Trail - Pinckney Trail - (TIRZ 21) 2021, adding 49 calendar days, with an addition in the amount of $16,927.19, Job No. (TIRZ 21), UPIN 22102MF2D501, Precinct 2, MWBE Contracted Goal: 25%, MWBE Current Participation: 100%.
Due Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. (TIRZ 21), UPIN 22102MF2D501
Vendor/Entity Legal Name (if applicable): McCory Engineering

MWBE Contracted Goal (if applicable): 25%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with McCory Engineering in connection with the construction of Trail - Pinckney Trail - (TIRZ 21) 2021, adding 49 calendar days, with an addition in the amount of $16,927.19, Job No. (TIRZ 21), UPIN 22102MF2D501, Precinct 2, MWBE Contracted Goal: 25%, MWBE Current Participation: 100%.
end

Background and Discussion:
The Pinckney Trail Connection project consists of constructing a 10-ft-wide hike and bike trail from the White Oak Bayou Greenway Trail to the intersection of Fletcher Street and Pinckney Street. The project will also include a proposed 200- ft long retaining wall with a concrete swale, approximately 900 LF of varying size storm sewer along with inlets and manholes, a headwall, grass-lined swales, bollards, permanent street and trail signs, handrails, waterline and sanitary line adjustments, benches, trash receptacles, and pavement markings accompanying the trail in Harris County Precinct 2.

The Changes in contract include:
* A new line item of 4 modified Inlets is needed due to shift in the trail alignment in order to avoid the power pole relocation with an additional cost of $16,927.19 and 14 calendar days.
* Additional 35 calendar...