Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, P.E.
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): UPIN 24103MF3C501
Vendor/Entity Legal Name (if applicable): Harris County Municipal District No. 500
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an interlocal agreement with Harris County Municipal District No. 500 for improvements to drainage facilities in and around the extension of Mound Road from Greenhouse Road to West Drive, UPIN 24103MF3C501, Precinct 3.
end
Background and Discussion:
Caldwell (developer) donated a 30' drainage easement to MUD 500. According to an agreement between the developer, MUD, and HC, the County will first construct Mound Rd, including a temporary plastic outfall, while TxDOT finalizes their design for US 290 at Greenhouse project. TxDOT requested to replace the plastic pipe and install an RCP to meet Greenhouse and Mound Rd drainage requirements and take ownership of the easement and maintenance responsibilities.
Agreement is to remove and replace the plastic pipe with RCP to meet Greenhouse and Mound Rd drainage requirements and take ownership of the easement and maintenance responsibilities.
Expected Impact:
It is of mutual benefit to both Parties (Office of the County Engineer and Harris County Municipal Utility District No. 500) to follow TxDOT's standard construction requirements for improvements to drainage facilities in and arou...