File #: 25-3566    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/28/2025 In control: Commissioners Court
On agenda: 6/12/2025 Final action: 6/12/2025
Title: Request for approval of a change in contract with Environmental Allies Inc, in connection with Mound Road Extension from Greenhouse Road along Spring Drive to Cypress Drive, adding 2 calendar days, with an addition in the amount of $46,561.39, Job No. 24/0076-1, UPIN 21208MF1QS01, Precinct 3, MWBE Contracted Goal: 30%, MWBE Current Participation: 19.52%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0076, UPIN 21208MF1QS01
Vendor/Entity Legal Name (if applicable): Environmental Allies Inc

MWBE Contracted Goal (if applicable): 30%
MWBE Current Participation (if applicable): 19.52%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Environmental Allies Inc, in connection with Mound Road Extension from Greenhouse Road along Spring Drive to Cypress Drive, adding 2 calendar days, with an addition in the amount of $46,561.39, Job No. 24/0076-1, UPIN 21208MF1QS01, Precinct 3, MWBE Contracted Goal: 30%, MWBE Current Participation: 19.52%.
end

Background and Discussion:
Project included the construction Mound Road Extension from Greenhouse to Cypress Drive. This project extends Mound Road past the intersection with Greenhouse Road to 0.86 miles east of Greenhouse Road. Starting at Greenhouse Road, a 4-lane concrete pavement section with a grass median will be constructed. The pavement section will then transition to a 41-foot-wide concrete section for the remaining portion of
the project.

The change in contract includes the following:
* Concrete Pump 200' Hose $2,684.00
* Precast Concrete Manhole 4' Diameter $7,184.88
* Precast Concrete Manhole 5' Diameter $8,898.48
* Inlet Protection Barrier Stage 1 $1,337.76
* Temporary Message Sign Board and New Pattern Sign $13,556.95
* The final adjustment (reconciliation of actual quantities used in construction...