File #: 25-3219    Version: 1 Name:
Type: Utility Agreement Status: Passed
File created: 5/9/2025 In control: Commissioners Court
On agenda: 5/22/2025 Final action: 5/22/2025
Title: Request for approval to execute a Utility Adjustment Agreement with Kinder Morgan Texas Pipeline, LLC in the amount of $2,378,052.00 to relocate utilities in connection with Roland Road and Related Infrastructure Drainage Improvements - 2018, UPIN 19103MF14C01, Precinct 4.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

Project ID (if applicable): UPIN 19103MF14C01
Vendor/Entity Legal Name (if applicable): Kinder Morgan Texas Pipeline LLC

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute a Utility Adjustment Agreement with Kinder Morgan Texas Pipeline, LLC in the amount of $2,378,052.00 to relocate utilities in connection with Roland Road and Related Infrastructure Drainage Improvements - 2018, UPIN 19103MF14C01, Precinct 4.
end

Background and Discussion:
The project is located within the South Mayde Creek Watershed in western Harris County. The Roland Road subdivision consists of mainly roadside ditches and has been subjected to several flooding events. The scope and proposed improvements include surface collection, ditch grading and storm sewer conveyance of the drainage along Roland Road. The existing HCFCD U201-09-00 channel will be extended from Porter Road to Katy Hockley Cutoff Road to provide reduction in inundation of the subdivision. This Utility Adjustment Agreement allows the project to move forward with the improvements by relocating the pipeline facilities that are in conflict with the proposed improvements.

Expected Impact:
This project seeks to reduce flood risk and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. This agreement is a step ...