Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0263, UPIN 211033020802-3
Vendor/Entity Legal Name (if applicable): Earth Builders, LP
MWBE Contracted Goal (if applicable): 29%
MWBE Current Participation (if applicable): 32.07%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Earth Builders, LP, in connection with final construction of John Paul Landing - North Basin Cell Phase 3, with a deduction in the amount of $76,071.00, Job No. 23/0263-3, UPIN 211033020802-3, Precinct 4, MWBE Contracted Goal: 29%, MWBE Current Participation: 32.07%.
end
Background and Discussion:
The project involves constructing the third and final phase of the John Paul Landing Detention Basin master plan. Its goal is to provide a stormwater quality detention pond, achieving the full intended functionality of the basin to enhance drainage and reduce flooding risks. The project was overseen by the Office of County Engineer.
This final change order is for a deduction of the final adjustment in the amount of $76,071.00 and includes quantity adjustments of existing items for final values.
Final Adjustment is the reconciliation of actual quantities used in construction against the bid quantities.
Added Items:
? PCO #3 - Final Adjustment: ($76,071.00), Zero Days
Expected Impact:
The final change ensures the contractor receives payment for the final pay estimates, including the retainage, while allowing unused funds to be returned to the precin...