Legislation Details

File #: 25-3195    Version: 1 Name:
Type: Utility Agreement Status: Passed
File created: 5/9/2025 In control: Commissioners Court
On agenda: 5/22/2025 Final action: 5/22/2025
Title: Request for approval to execute a Service Outlet Location Statement (SOLS) with CenterPoint Energy to install eight (8) braces on the primary poles, in multiple locations, in connection with Humble Road Place and Parkland Estates Subdivisions Drainage Improvements - 2018, UPIN 21090MF22H01, Precincts 1 and 2.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

Project ID (if applicable): UPIN 21090MF22H01
Vendor/Entity Legal Name (if applicable): CenterPoint Energy

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable):N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable):N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute a Service Outlet Location Statement (SOLS) with CenterPoint Energy to install eight (8) braces on the primary poles, in multiple locations, in connection with Humble Road Place and Parkland Estates Subdivisions Drainage Improvements - 2018, UPIN 21090MF22H01, Precincts 1 and 2.

end

Background and Discussion:
The project includes Drainage and Infrastructure Improvements for and related to Humble Road Place and Parkland Estates Subdivisions. The work includes base repairs, mill and overlays, ditch regrading, culvert replacements, and adjustments around eight (8) poles in different location which are in the Harris County ROW. CenterPoint Energy to install Brace, for the eight (8) poles, and remove all braces after conclusion of the project.


Expected Impact:
This action allows the continuation of the contracted work.

Alternative Options:
If no action is taken, the project may experience construction delays.




County Strategic Plan Goal: 1. Make Harris County safer and more just.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): ...

Click here for full text