Title: Transmittal by the Flood Control District of a substantial completion certificate with A Morfin Trucking, LLC, for the Baywood Stormwater Detention Basin (Armand Bayou Watershed, Bond ID F-72, Project ID B513-02-00-E003, Job No. 24/0188, Precinct 2).
Attachments: 1. .B513-02-00-E003 Certificate of Substantial Completion - signed.pdf
Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

Project ID (if applicable): B513-02-00-E003
Vendor/Entity Legal Name (if applicable): A Morfin Trucking, LLC

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Transmittal by the Flood Control District of a substantial completion certificate with A Morfin Trucking, LLC, for the Baywood Stormwater Detention Basin (Armand Bayou Watershed, Bond ID F-72, Project ID B513-02-00-E003, Job No. 24/0188, Precinct 2).
end

Background and Discussion:
The purpose of this transmittal is to submit the Certificate of Substantial Completion, confirming that the Contractor has fulfilled the scope of work and resolved all punch list items to the satisfaction of the Flood Control District.

Expected Impact:
Substantial Completion signifies that a flood control project is largely finished, allowing the Flood Control District to begin using the majority of the infrastructure to realize intended flood risk reduction benefits while the Contractor completes any applicable minor outstanding details.

Alternative Options:
There is no viable alternative to accepting substantial completion when a Contractor successfully completes the work scope of a contract.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other inf...