Legislation Details

File #: 25-3043    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/6/2025 In control: Commissioners Court
On agenda: 5/22/2025 Final action: 5/22/2025
Title: Request for approval of change in contract No. 3 with Liberty Construction Group, Inc., for the Addicks Watershed Repair Package 2, adding 28 calendar days (Bond ID F-53, Project ID Z100-00-00-X323, Job No. 23/0116, Precinct 4, MWBE Contracted Goal: 31%, MWBE Current Participation: 40.36%).
Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Z100-00-00-X323
Vendor/Entity Legal Name (if applicable): Liberty Construction Group, Inc.

MWBE Contracted Goal (if applicable): 31%
MWBE Current Participation (if applicable): 40.36%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 3 with Liberty Construction Group, Inc., for the Addicks Watershed Repair Package 2, adding 28 calendar days (Bond ID F-53, Project ID Z100-00-00-X323, Job No. 23/0116, Precinct 4, MWBE Contracted Goal: 31%, MWBE Current Participation: 40.36%).
end

Background and Discussion:
This change in contract is needed to complete the construction contract for this project. Project Z100-00-00- X323 represents a combination of construction activities of three (3) different Project IDs located in the Addicks Reservoir (U) Watershed in Harris County, Texas. Several channels have experienced erosion and structural failures during recent storm events, and repairs are needed to ensure they function properly and safely. The objective of this Project is to repair failures within the project limits. Repairs include, but are not limited to, installing rock, rebuilding side slopes, replacing inlet structures and storm outfalls, removing sediment, and replacing concrete channel lining.

The purpose of this contract change is to adjust the final quantities of several bid items that their completed quantities were more than contract original quantities, deduct the unused quantities of...

Click here for full text