Legislation Details

File #: 25-3037    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 5/6/2025 In control: Commissioners Court
On agenda: 5/22/2025 Final action: 5/22/2025
Title: Request for approval of change in contract No. 3 with Allgood Construction Co Inc., for the White Oak Bayou Federal Flood Damage Reduction Project, adding 276 calendar days (White Oak Bayou Watershed, Bond ID C-14, Project ID E100-00-00-E007, Job No. 23/0115, Precinct 1, MWBE Contracted Goal: 26%, MWBE Current Participation: 9.26%).
Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): E100-00-00-E007
Vendor/Entity Legal Name (if applicable): Allgood Construction Co Inc.

MWBE Contracted Goal (if applicable): 26%
MWBE Current Participation (if applicable): 9.26%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 3 with Allgood Construction Co Inc., for the White Oak Bayou Federal Flood Damage Reduction Project, adding 276 calendar days (White Oak Bayou Watershed, Bond ID C-14, Project ID E100-00-00-E007, Job No. 23/0115, Precinct 1, MWBE Contracted Goal: 26%, MWBE Current Participation: 9.26%).
end

Background and Discussion:
This change in contract is needed to complete the construction contract for this project. Federal Flood Control
Project Channel Modifications Discrete Segment 104 White Oak Bayou Cole Creek to Hollister Street includes
the installation of approximately 1.65 miles of 10-foot to 12-foot width concrete sidewalk bike trails, concrete
sidewalk pedestrian access paths and wheelchair ramps, and excavation and regrading approximately 4.65 miles of drainage channel, including installation of backslope swales.

The purpose of this contract change is to adjust excavation, Grade 1 Riprap, and Headwall/Wingwall quantities to address discrepancies revealed after conducting an intermediate survey to document site conditions left behind by the previous contractor after reaching an agreement with the surety. This contract change also adds a new pay item due to unforesee...