Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Supplemental RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0143, UPIN 23103MF2VW01
Vendor/Entity Legal Name (if applicable): Texas Materials Group, Inc.
MWBE Contracted Goal (if applicable): 32%
MWBE Current Participation (if applicable): 29.07%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request by the Office of the County Engineer for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Asphalt Package 2023-1, adding 21 calendar days, with an addition in the amount of $507,266.04, Job No. 23/0143-2, UPIN 23103MF2VW01, Precinct 3, MWBE Contracted Goal: 32%, MWBE Current Participation: 29.07%.
end
Background and Discussion:
The project includes roadway rehabilitation of a Cypress North Houston from Jones Road to Perry Road, Telge Road from Kitzman to Grand Parkway, Jones Road from Farm To Market 1960 to Cypress North Houston Road, North Eldridge at South of Lakewood Meadow Drive, Boudreaux Road from Hufsmith-Kohrville to Grand Parkway, Hufsmith-Kohrville from Grand Parkway to Food Control Channel, Hufsmith Road from Farm to Market 2978 to Burroughs Park, and intersection improvement for Telge Road at Boudreaux Road.
This change in contracts includes:
* Time due for CenterPoint to connect power to the signal. (21 days)
* Cost of slurry for drill shaft foundation. ($5,082.00)
* The final adjustment (reconciliation of actual quantities used in construction against the bid quantities). ($502,184.05)
Expected Impac...
Click here for full text