Legislation Details

File #: 25-2024    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/18/2025 In control: Commissioners Court
On agenda: 3/27/2025 Final action: 3/27/2025
Title: Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with West Gulf Bank Road from I45 to Airline Drive, adding 10 calendar days, with an addition in the amount of $26,698.77, Job No. 22/0461-7, UPIN 19101MF0XV01, Precinct 2, MWBE Contracted Goal: 25%, MWBE Current Participation: 29.29%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 22/0461, UPIN 19101MF0XV01
Vendor/Entity Legal Name (if applicable): Allgood Construction Co., Inc.

MWBE Contracted Goal (if applicable): 25%
MWBE Current Participation (if applicable): 29.29%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Allgood Construction Co., Inc., in connection with West Gulf Bank Road from I45 to Airline Drive, adding 10 calendar days, with an addition in the amount of $26,698.77, Job No. 22/0461-7, UPIN 19101MF0XV01, Precinct 2, MWBE Contracted Goal: 25%, MWBE Current Participation: 29.29%.
end

Background and Discussion:
This project includes the construction of four 11-foot-wide concrete pavement with a 24-foot median, and 8-foot-wide sidewalk along both sides West Gulf Bank Road from Interstate 45 Freeway to Airline Drive. It also includes the drainage improvements.

The change order includes the following:
- During the construction phase Driveway 9-1, an elevation difference was identified between the existing parking lot entrance and the proposed driveway. After coordination with the project stakeholders, it was determined that the best approach would be to adjust the driveway and sidewalk elevations to align properly. To facilitate this adjustment, the contractor will need to temporarily remove the existing gate to reconstruct the driveway. This change order will add 4 days and additional cost of $14,015.49 to the contract.
- The propos...

Click here for full text