Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): UPIN 19101MF16P01
Vendor/Entity Legal Name (if applicable): CenterPoint Energy Houston Electric, LLC
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute a Grant to Others Agreement for installation of a Harris County driveway across CenterPoint Right of Way for Ralston Acres Subdivision Drainage Improvements-2018, UPIN 19101MF16P01, Precinct 1.
end
Background and Discussion:
Ralston Acres is in northeast Harris County, Precinct 1. The project site is generally bounded by Greens Bayou (P100-00-00) to the west, Spicewood Ln to the north, CE King Parkway to the east and the Beaumont Freeway (Business US 90) to the south. The local drainage system is composed of roadside ditches less than two feet deep and driveways culverts. The proposed improvements include the design of an enclosed storm sewer system with a shallow swale above along John Ralston Road. The project also includes a wet bottom detention basin to mitigate adverse impacts not only for the Ralston Acres project but also for a portion of the Houmont Park Drainage Improvements project proposed to the north and east of subdivision. This agreement will permit the construction of a driveway across the CenterPoint Right of Way in Harris County, allowing access for maintenance vehicles both during and after construction.
Expected Impact:
This project seeks to reduce ...