Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0491, UPIN 23101MF2PJ01
Vendor/Entity Legal Name (if applicable): McKenna Contracting, Inc.
MWBE Contracted Goal (if applicable): 21%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with McKenna Contracting, Inc. in connection with final construction of Gene Green Park-All Inclusive Playground-2022, adding 32 calendar days, with a deduction in the amount of $22,193.03, Job No. 23/0491-2, UPIN 23101MF2PJ01, Precinct 1, MWBE Contracted Goal: 21%, MWBE Current Participation: 100%.
end
Background and Discussion:
The additional works are due to the new water line for water fountain relocation and for the installation of decomposed granite.
Expected Impact:
Relocating new water line for water fountain and placing decomposed granite(DG) will make the new playground beautiful and children are more safe to play around.
Alternative Options:
N/A
County Strategic Plan Goal: 1. Make Harris County safer and more just.
County Strategic Plan Objective: P: Improve children's health outcomes.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): I1: Develop a countywide parks network and connectivity plan.
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes related to ...
Click here for full text