Legislation Details

File #: 25-1774    Version: 1 Name:
Type: Transmittal Status: Accepted
File created: 3/13/2025 In control: Commissioners Court
On agenda: 3/27/2025 Final action: 3/27/2025
Title: Transmittal by the Office of the County Engineer of a substantial completion certificate with Formative Structures, LLC, in connection with Barbara Jordan Park - Pavilion and Drainage Improvements - 2021, Job No. 23/0352, UPIN 21101MF23401, Precinct 1, MWBE Contracted Goal: 29%, MWBE Current Participation: 31.16%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E, PMP, CFM, ENV-SP, County Engineer
Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

Project ID (if applicable): 23/0352
Vendor/Entity Legal Name (if applicable): Formative Structures, LLC
MWBE Contracted Goal (if applicable): 29%
MWBE Current Participation (if applicable): 31.16%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Transmittal by the Office of the County Engineer of a substantial completion certificate with Formative Structures, LLC, in connection with Barbara Jordan Park - Pavilion and Drainage Improvements - 2021, Job No. 23/0352, UPIN 21101MF23401, Precinct 1, MWBE Contracted Goal: 29%, MWBE Current Participation: 31.16%.
end

Background and Discussion:
The original basketball pavilion immediately adjacent to the community center at Barbara Jordan Park was evaluated for structural integrity after damage was observed at the bases of the steel columns. The purpose of this contract change is to reconcile quantities and extend contract duration to fifty-one additional days (thirty days for the drainage system, fourteen days due to inclement weather and park closure and seven days for painting the underside of pavilion.

Completion Date for this project is established to be February 10th, 2025

Expected Impact:
This action establishes the date on which a capital improvement enters service as a Harris County asset.

Alternative Options:
N/A
County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy I...

Click here for full text