Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Transmittal
Project ID (if applicable): U520-01-00-E004, D518-03-00-E002, P100-00-00-E014
Vendor/Entity Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Transmittal by the Flood Control District of the executed amendment to the agreement with the Texas General Land Office to approve three projects for the CDBG-DR Program (24-033-000-E072) and to extend the CDBG-DR grant end date to February 28, 2027.
end
Background and Discussion:
The purpose of this transmittal is to inform Commissioner's Court of the second amendment to the CDBG-DR Contract (24-033-000-E072), which adds three projects to the contract and extends the CDBG-DR program deadline to February 28, 2027. The CDBG-DR contract was approved by Commissioners Court on October 31, 2023, and was amended on June 4, 2024 to include seven General Land Office (GLO) approved applications. As additional applications are approved by the GLO, the CDBG-DR contract will be further amended to include those projects.
The three projects being amended into the contract include the following:
* Dinner Creek Stormwater Detention Basin - Phase 1 (U520-01-00-E004)
* Keegans Bayou Detention Basin near Old Richmond Road-Phase 1 (D518-03-00-E002)
* Greens Bayou Mid-Reach Channel Conveyance Improvements (P100-00-00-E014)
The seven projects that have already been amended into the contract include the following:
* Arbor Oaks Stormwate...
Click here for full text