Legislation Details

File #: 25-1673    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/12/2025 In control: Commissioners Court
On agenda: 3/27/2025 Final action: 3/27/2025
Title: Request for approval of an amendment to an agreement with IDCUS, Inc., in the amount of $357,821, to provide design update, bidding, and construction phase engineering services in support of the West Little York Stormwater Detention Basin project, previously Langham Creek Regional Stormwater Detention Basin Phase II (Addicks Reservoir Watershed, Bond ID C-37, Project ID U500-01-00-E002, Agreement No. 2018-103, Precinct 4, MWBE Contracted Goal: 9.6%, MWBE Current Participation: 25.48%).
Attachments: 1. 032725 AMEND IDCUS 2018-103 PCT 4 backup.pdf
Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): U500-01-00-E002
Vendor/Entity Legal Name (if applicable): IDCUS, Inc.

MWBE Contracted Goal (if applicable): 9.6%
MWBE Current Participation (if applicable): 25.48%
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with IDCUS, Inc., in the amount of $357,821, to provide design update, bidding, and construction phase engineering services in support of the West Little York Stormwater Detention Basin project, previously Langham Creek Regional Stormwater Detention Basin Phase II (Addicks Reservoir Watershed, Bond ID C-37, Project ID U500-01-00-E002, Agreement No. 2018-103, Precinct 4, MWBE Contracted Goal: 9.6%, MWBE Current Participation: 25.48%).
end

Background and Discussion:
This amendment will provide design update, bidding, and construction phases services for the West Little York Stormwater Detention Basin. The project entails the design and construction of three stormwater detention basins along Langham Creek. Site conditions have changed since the final plans were completed in 2020, necessitating an update to the construction plans and related due diligence. This project occurs in the 3rd quartile under the 2022 Prioritization Framework approved by Commissioners Court.

Expected Impact:
The project seeks to reduce flood risks and strengthen resiliency in the Addicks Reservoir watershed by providing approximately 100 ac-ft of detention storage along Langham Creek.



Alternative Op...

Click here for full text