Title: Transmittal by the Office of the County Engineer of a substantial completion certificate with Frost Construction Company, Inc., in connection with the Baldwin Boettcher Library Mitigation (Harvey), Job No. 22/0424, UPIN 18035MF0WG01, Precinct 3, MWBE Contracted Goal: 17%, MWBE Current Participation: 20.60%.
Sponsors: Mony Hossain
Attachments: 1. Transmittal-18035MF0WG01-Frost Construction , IncAldine Westfield-Baldwin Boettcher Library - P3 vr 1
Primary Department: County Engineer
Primary Department Head/Elected Official: Dr. Milton Rahman, PhD, P.E, PMP, CFM, ENV-SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S Ramsey
Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

Project ID (if applicable): 22/0424
Vendor/Entity Legal Name (if applicable): Frost Construction Company, Inc.

MWBE Contracted Goal (if applicable): 17%
MWBE Current Participation (if applicable): 20.60%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Transmittal by the Office of the County Engineer of a substantial completion certificate with Frost Construction Company, Inc., in connection with the Baldwin Boettcher Library Mitigation (Harvey), Job No. 22/0424, UPIN 18035MF0WG01, Precinct 3, MWBE Contracted Goal: 17%, MWBE Current Participation: 20.60%.
end

Background and Discussion:
The Baldwin Boettcher Branch Library is located inside the Mercer Botanic Gardens at 22306 Aldine Westfield
Rd, Humble, TX 77338. The disaster recovery project involves the repair of damage caused by Hurricane Harvey in August 2017, including wall and floor finishes, mechanical, electrical, plumbing, and data fixtures and equipment. This change in contract has removed data scope of work from the general contractor to Harris County which includes cost and labor.

Completion Date for this project is established to be September 4th, 2024

Expected Impact:
This action establishes the date on which a capital improvement enters service as a Harris County asset.

Alternative Options:
N/A
County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Econo...