Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): C143-00-00-E001
Vendor/Entity Legal Name (if applicable): AKV Consultants, LLC
MWBE Contracted Goal (if applicable): 20%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an agreement with AKV Consultants, LLC, in the amount of $1,435,764, to provide preliminary engineering, design, bidding, and construction phase engineering services in support of conveyance improvements along HCFCD Unit C143-00-00 (Sims Bayou Watershed, Bond ID F-94, Project ID C143-00-00-E001, Agreement No. 2023-37, Precinct 1, MWBE Contracted Goal: 20%).
end
Background and Discussion:
This agreement will provide preliminary engineering, design, bidding, and construction phase services for Tributary C143-00-00 Conveyance Improvements. This project was recommended by the C143-00-00 feasibility study and consists of conveyance improvements along tributary C143-00-00, as well as providing detention storage needed to mitigate the impacts of the upsized 7' x 7' reinforced concrete boxes (RCB) culvert at Anderson Road. This project occurs in the 3rd quartile under the 2022 Prioritization Framework approved by Commissioners Court.
Expected Impact:
The project seeks to reduce flood risks and strengthen resiliency in the Sims Bayou watershed by improving conveyance along HCFCD Unit C143-00-00.
Alternative Options:
The alternative to approving this item would be not proceeding with this project, which wou...
Click here for full text