Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Flood Control District
Secondary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Regular or Supplemental RCA: Regular RCA
Type of Request: Asset Management
Project ID (if applicable): 24090MF34101
Vendor/Entity Legal Name (if applicable): Not applicable
MWBE Contracted Goal (if applicable): Not applicable
MWBE Current Participation (if applicable): Not applicable
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): Not applicable
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval for County of Harris, a body corporate and politic under the laws of the State of Texas to convey real estate to Harris County Flood Control District, a political subdivision of the State of Texas, M124-00-00-01-008.0, a 30.80 acre Drainage Easement for HCFCD Dedications project and that the County Judge execute the Drainage Easement, UPIN 24090MF34101, Precinct 4.
end
Background and Discussion:
Harris County is requesting HCFCD take the basin into HCFCD maintenance, HCFCD requires an easement for maintenance.
Expected Impact:
HCFCD will maintain the basin.
Alternative Options:
Harris County will be responsible for the maintenance if the easement is not dedicated.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: R: Enhance disaster preparedness, response, recovery, and resiliency.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): H2: Evaluate the feasibility and potential impacts of substantial, large-scale flood mitigation measures to provide equitable an...