Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0420, UPIN 14104MF08X01
Vendor/Entity Legal Name (if applicable): Main Lane Industries, LLC
MWBE Contracted Goal (if applicable): 27%
MWBE Current Participation (if applicable): 23.53%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with MC2 Civil, LLC in connection with construction of Treaschwig Road A (Phase 1) - from 1,000' West of Aldine Westfield Road to West of Cypress Creek - 2014, adding 152 calendar days, with an addition in the amount of $182,900.29, Job No. 23/0420-1, UPIN 14104MF08X01, Precinct 3, MWBE Contracted Goal: 27%, MWBE Current Participation: 23.53%.
end
Background and Discussion:
The project consists of construction of Treaschwig Road Segment A Phase 1 project consists of reconstruction and widening of Treaschwig Road from a 2-lane asphalt to a 4-lane concrete roadway from 1000' west of Aldine Westfield to west of Cypress Creek. Additionally, extend intersection improvements at Aldine Westfield by 500' North and South of Treaschwig Road. Project will construct a wet bottom detention pond adjacent to Cypress Creek.
This change in contracts includes:
* Change includes cost and time for EZ fiber conflict delay ($287,883.68 - 3 days).
* Cost of adding new bid item for additional clearing for installation of outfall at detention basin ($9,376.61).
* Cost includes quantity adjustment for profile modification requested by Precinct 3 to avoid potential private fences and gates relocation along the Right-of-Way (-$114,360.00).
Expected Impact:
Change allows the contractor to be...