Title: Request for approval to execute an interlocal agreement with Harris County Municipal Utility District No. 570C for non-standard maintenance of construction of a pedestrian tunnel, C402 combination rail, headwalls, skylight, and related appurtenances within the existing right-of-way of Kickapoo and Betka, UPIN NS104, ePermits: 2403220158, Precinct 4.
Attachments: 1. 25-1495-Partnership-NS104-HCMUD 570C-P4-03272025
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official:

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

Project ID (if applicable): NS104, ePermits: 2403220158
Vendor/Entity Legal Name (if applicable): Harris County Municipal Utility District No. 570C

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an interlocal agreement with Harris County Municipal Utility District No. 570C for non-standard maintenance of construction of a pedestrian tunnel, C402 combination rail, headwalls, skylight, and related appurtenances within the existing right-of-way of Kickapoo and Betka, UPIN NS104, ePermits: 2403220158, Precinct 4.
end

Background and Discussion:
This project is to provide connectivity of residents to a recreation center to construction of a pedestrian tunnel and TXDOT Type C402 combination rail, located 0.5 miles south of the intersection of Kickapoo Road and Betka Road, headwalls, and skylight.

Expected Impact:
This project will bring improvements to pedestrian safety through development.

Alternative Options:
An at-grade crossing or pedestrian bridge would be other options but may be cost prohibitive.


County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A

Additional note...

Click here for full text