Title: Request for approval of a change in contract with Frost Construction Co. Inc. in connection with 15430 East Freeway 'IH-10E' - East Harris County Healthcare and Social Services Hub - 2024, adding 30 calendar days, with an addition in the amount of $25,620.75, UPIN 21102MF1QB01, Precinct 2, MWBE Contracted Goal: 16%, MWBE Current Participation: 16%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Secondary Department: Commissioner, Precinct 2
Secondary Department Head/Elected Official: Commissioner Adrian Garcia

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 21102MF1QB01 Job ID: 230369
Vendor/Entity Legal Name (if applicable): Frost Construction Co. Inc.

MWBE Contracted Goal (if applicable): 16%
MWBE Current Participation (if applicable): 16%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Frost Construction Co. Inc. in connection with 15430 East Freeway 'IH-10E' - East Harris County Healthcare and Social Services Hub - 2024, adding 30 calendar days, with an addition in the amount of $25,620.75, UPIN 21102MF1QB01, Precinct 2, MWBE Contracted Goal: 16%, MWBE Current Participation: 16%.
end

Background and Discussion:
East Harris County Healthcare & Social Services Hub is a 10,650 square foot building that will provide wrap -around healthcare and social services for the East Harris community. This new facility will be located at 15430 East Fwy, Channelview, TX 77530. The project is primarily funded through CDBG-DR with matching funds from
Precinct 2 & Public Health. Change Order includes:
1) Rental of one mobile generator and supply of fuel to run it. This was required to supply power to the site office and construction activities. $4,579.11.
2) Daiken HVAC Roof Top Units (RTUs) order was canceled by the County due to long delivery schedule of up to 40 weeks. Cancellation fee was imposed in accordance with procurement agreement. $12,052.85.
3) Building doors hardware are being upgraded with card access r...