Legislation Details

File #: 25-1474    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/5/2025 In control: Commissioners Court
On agenda: 3/27/2025 Final action: 3/27/2025
Title: Request for approval of a change in contract with GLM Contracting, Inc. in connection with final construction of Intersection Improvement - Huffmeister at SH 6 - 2022, with an addition in the amount of $19,891.01, Job No. 22/0019-1, UPIN 23103MF2R001, Precinct 3, MWBE Contracted Goal: 19%, MWBE Current Participation: 30.87%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 22/0019, UPIN 23103MF2R001
Vendor/Entity Legal Name (if applicable): GLM Contracting, Inc.

MWBE Contracted Goal (if applicable): 19%
MWBE Current Participation (if applicable): 30.87%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with GLM Contracting, Inc. in connection with final construction of Intersection Improvement - Huffmeister at SH 6 - 2022, with an addition in the amount of $19,891.01, Job No. 22/0019-1, UPIN 23103MF2R001, Precinct 3, MWBE Contracted Goal: 19%, MWBE Current Participation: 30.87%.
end

Background and Discussion:
The project involved constructing a southbound right-turn lane with 250 feet of storage and a 200-foot taper, as well as a 5-foot-wide sidewalk along the west side of Huffmeister Road. This sidewalk extends from SH 6 to approximately 400 feet north. The initiative aimed to improve and ensure a safe, reliable transportation route for Harris County residents at the existing intersection. Oversight was provided by the Office of the County Engineer Construction Programs Division team.
Changes include reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes.

- PCO - 1, Per PCT 3's approval, 1 Acre Hydromulch to be used to restore median - $3,209.70.






Expected Impact:
Changes allow for addition of new bid items to complete the project in accordance with the original intent of th...

Click here for full text