Legislation Details

File #: 25-1464    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 3/5/2025 In control: Commissioners Court
On agenda: 3/27/2025 Final action: 3/27/2025
Title: Request for approval to execute an agreement with Texas Urban Low Impact Development, LLC, dba White Oak Engineers & Planners in the amount of $73,843.00, for Construction Phase Services in connection with Connectivity Project - Curtis M. Graves - 2020, Job No. 24/0413, UPIN 20101MF1JE01, Precinct 1, MWBE Contracted Goal: 4.32%.
Attachments: 1. Award-UPIN 20101MF1JE01-CPS-Connectivity Project - Curtis M Graves-White Oak Engineers and Planners-P1-0327202.pdf
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): UPIN 20101MF1JE01 - Job No. 24/0413
Vendor/Entity Legal Name (if applicable): Texas Urban Low Impact Development, LLC, dba White Oak Engineers & Planners

MWBE Contracted Goal (if applicable): 4.32%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Texas Urban Low Impact Development, LLC, dba White Oak Engineers & Planners in the amount of $73,843.00, for Construction Phase Services in connection with Connectivity Project - Curtis M. Graves - 2020, Job No. 24/0413, UPIN 20101MF1JE01, Precinct 1, MWBE Contracted Goal: 4.32%.
end

Background and Discussion:
The project is to construct approximately 6,900 linear feet of 10' wide concrete trail along the top of bank of Homestead Detention Pond. The project also includes the construction of concrete driveway, 12-space parking lot, and park site amenities.

Expected Impact:
This action will allow Texas Urban Low Impact Development, LLC, dba White Oak Engineers & Planners to support the construction of the project.

Alternative Options:
If no action is taken, the engineer of record will not be accessible for support through the construction of the
project.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: I: Increase access to safe, clean, and enjoyable green space.
Justice/...

Click here for full text