Title: Request for approval to execute an agreement with Michael Baker International, Inc. in the amount of $1,405,668.00 for Professional Engineering Services in connection with Corridor Study - Irvington Blvd. from Fulton St. to Hardy Toll Road - 2023, UPIN 24102MF37X01, Precinct 2, MWBE Contracted Goal: 19.6%.
Attachments: 1. Award-24102MF37X01-Michael Baker International Inc.,Consultants-Corridor Study P2.pdf
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): UPIN: 24102MF37X01
Vendor/Entity Legal Name (if applicable): Michael Baker International, Inc.

MWBE Contracted Goal (if applicable): 19.6%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Michael Baker International, Inc. in the amount of $1,405,668.00 for Professional Engineering Services in connection with Corridor Study - Irvington Blvd. from Fulton St. to Hardy Toll Road - 2023, UPIN 24102MF37X01, Precinct 2, MWBE Contracted Goal: 19.6%.
end

Background and Discussion:
To meet Revive2Thrive vision of Precinct 2 for empowering communities and creating opportunities to existing neighborhoods, the project will study, evaluate, and analyze for roadway, drainage, and sidewalk improvements on Irvington Boulevard from Fulton Street to Hardy Toll Road.

Expected Impact:
The use of Professional Services will expedite the assessment of the existing roadway, drainage, and pedestrian elements of the Corridor; and provide recommendations using specialized engineering services.

Alternative Options:
The County could elect to fund the requested task or choose to reject it. However, if not approved, the contractor will not be able to complete the original scope of work.



County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve t...