Primary Department: Purchasing
Primary Department Head/Elected Official: Paige McInnis
Secondary Department: Commissioner, Precinct 4
Secondary Department Head/Elected Official: Lesley Briones
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 210259
Vendor/Entity Legal Name (if applicable): Highway 1, LLC
MWBE Contracted Goal (if applicable): 34%
MWBE Current Participation (if applicable):
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request for approval of an extension with Highway 1, LLC for paint striping of various roads at the Lyons Camp area and related items for Precinct 4 through May 31, 2025, or until a new contract is in place, with no increase in pricing (210259), MWBE Contracted Goal: 34%.
end
Background and Discussion:
Request for approval of extension with Highway 1, LLC for paint striping of various roads at the Tomball Services Center and related items in Precinct 4 for the period of March 5, 2025 - September 5, 2025, at a cost of $400,000. PCT 4 requested an extension of the contract related to paint striping of various roads at the Tomball Service Center and related items. Due to redistricting, the location was moved from Lyons Camp area to the Tomball Service Center.
Expected Impact:
PCT 4 will receive continued access to paint striping of various roads at the Tomball Service Center and related items.
Alternative Options:
PCT 4 will have to explore other options related to paint striping of various roads at the Tomball Service Center and related items.
County Strategic Plan Goal: N/A
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
...