Title: Request for approval of a change in contract with CE Barker Ltd., in connection with Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements aka Barrett Station Drainage Improvements, adding 69 calendar days, with no change in the amount, Job No. 23/0278-3, Grant Fund, UPIN 19102MF17801, Precinct 3, MWBE Contracted Goal: 26%, MWBE Current Participation: 39.96%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No: 23/0278, UPIN 19102MF17801
Vendor/Entity Legal Name (if applicable): CE Barker Ltd.

MWBE Contracted Goal (if applicable): 26%
MWBE Current Participation (if applicable): 39.96%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with CE Barker Ltd., in connection with Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements aka Barrett Station Drainage Improvements, adding 69 calendar days, with no change in the amount, Job No. 23/0278-3, Grant Fund, UPIN 19102MF17801, Precinct 3, MWBE Contracted Goal: 26%, MWBE Current Participation: 39.96%.
end

Background and Discussion:
Barrett Station (Phase 1 - Dreamland Place) Subdivision Drainage Improvements project is in the Northeast area of Harris County, east of FM 2100 and north of FM 1942. The scope of this project includes regrading roadside ditches, replace undersized driveway culverts, removal and replacement of driveways, road replacement in certain sections and construction of a dry bottom detention basin with pump station on the northeast corner of the subdivision, south of East Broussard.

The change in the contract includes the following:

* Added 69 calendar days to the project time for delay of Pump Station equipment delivery to complete the scope of work on the project.

This results in a net change in the amount of $0.00 and 69 calendar days.