File #: 25-1217    Version: 1 Name:
Type: Transmittal Status: Accepted
File created: 2/14/2025 In control: Commissioners Court
On agenda: 2/27/2025 Final action: 2/27/2025
Title: Transmittal by the Flood Control District of a preliminary engineering report for Channel Conveyance Improvements Along Goose Creek and Stormwater Detention Basin - Phase 1 prepared by Carollo, Inc., dated April 2023 (Spring Gully and Goose Creek Watersheds, Bond ID F-102, Project ID O100-00-00-E003, Precinct 2).
Attachments: 1. O100-00-00-E003 PBM.pdf
Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

Project ID (if applicable): O100-00-00-E003
Vendor/Entity Legal Name (if applicable): N/A

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Transmittal by the Flood Control District of a preliminary engineering report for Channel Conveyance Improvements Along Goose Creek and Stormwater Detention Basin - Phase 1 prepared by Carollo, Inc., dated April 2023 (Spring Gully and Goose Creek Watersheds, Bond ID F-102, Project ID O100-00-00-E003, Precinct 2).
end

Background and Discussion:
The purpose of this project is to reduce flood risk in the Spring Gully and Goose Creek Watersheds by designing channel conveyance improvements along Goose Creek and a stormwater detention basin (SWDB).

Expected Impact:
The acceptance of this PER will allow the Flood Control District to move into the engineering stage of this project and finalize design so that the project can be publicly bid for construction.

Alternative Options:
The alternative to approving this item would be not approving this Preliminary Engineering Report, which would result in the Flood Control District not proceeding with the final design of this project.

County Strategic Plan Goal: 5. Minimize the impact of climate change and disasters.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infra...

Click here for full text