Title: Request for approval to execute an agreement with STOA International Architects, Inc. in the amount of $57,610.00 to provide Professional Services for Programming Phase for Harris County Precinct 3 - Mathews Community Center located at 1728 East Hufsmith Road, Tomball, TX 77375, UPIN 25103MF3MY01, Precinct 3, MWBE Contracted Goal: 21.3%.
Attachments: 1. 25-1202-Award-UPIN 25103MF3MY01-MATHEWS-STOA-P3-02-27-2025
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom Ramsey, PE

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 25103MF3MY01
Vendor/Entity Legal Name (if applicable): STOA International Architects, Inc.

MWBE Contracted Goal (if applicable): 21.3%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): NA
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with STOA International Architects, Inc. in the amount of $57,610.00 to provide Professional Services for Programming Phase for Harris County Precinct 3 - Mathews Community Center located at 1728 East Hufsmith Road, Tomball, TX 77375, UPIN 25103MF3MY01, Precinct 3, MWBE Contracted Goal: 21.3%.
end

Background and Discussion:
Precinct 3 intends to provide a community center as part of a larger plan to redevelop existing Mathews Park. The new 1-story community center will include surface level parking and walking only trail adjacent to parking lot.

Expected Impact:
This will create a community center at this location.

Alternative Options:
If the court declines to approve the programming request, then the neighborhood will have the existing community building, which is currently only open by appoint and not large enough for the needs of community members.



County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): H4: Consistently ...