Legislation Details

File #: 25-1171    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 2/13/2025 In control: Commissioners Court
On agenda: 2/27/2025 Final action: 2/27/2025
Title: Request for approval of change in contract No. 4 with Rebel Contractors, Inc., for the Mud Gully Channel Conveyance Improvements Package 2, adding 27 calendar days (Clear Creek Watershed, Bond ID C-03, Project A120-00-00-C004, Job No. 20/0244A, Precinct 2, Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program).
Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): A120-00-00-C004
Vendor/Entity Legal Name (if applicable): Rebel Contractors, Inc.

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 4 with Rebel Contractors, Inc., for the Mud Gully Channel Conveyance Improvements Package 2, adding 27 calendar days (Clear Creek Watershed, Bond ID C-03, Project A120-00-00-C004, Job No. 20/0244A, Precinct 2, Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program).
end

Background and Discussion:
The purpose of this contract change is to extend the contract duration by 24 days (3 days for inclement weather and 21 days due to utility delays). Mud Gully Channel Conveyance Improvements Package 2 includes clearing and grubbing, excavating and disposing of material, constructing concrete channel lining, and removing and replacing storm sewer system components.

Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.