Title: Request for approval to execute an agreement with WSB, LLC in the amount of $177,705.20 for Professional Engineering and related services in connection with Asphalt Rehabilitation - Memorial Drive between Greenbay Street and West of Chimney Rock - 2024, and Asphalt Rehabilitation - Campbell Road - 2025, UPINs 25103MF3MT01 & 25103MF3N001, Precinct 3, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.
Attachments: 1. 25-1166-Award-UPIN 25103MF3MT01-PSA-Asphalt Rehabilitation-Memorial Drive-WSB LLC-P3-v01
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 25103MF3MT01 & 25103MF3N001
Vendor/Entity Legal Name (if applicable): WSB, LLC

MWBE Contracted Goal (if applicable): 0%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: 0% - Non-Divisible

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with WSB, LLC in the amount of $177,705.20 for Professional Engineering and related services in connection with Asphalt Rehabilitation - Memorial Drive between Greenbay Street and West of Chimney Rock - 2024, and Asphalt Rehabilitation - Campbell Road - 2025, UPINs 25103MF3MT01 & 25103MF3N001, Precinct 3, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.
end

Background and Discussion:
Precinct 3 is requesting the Office of the County Engineer to negotiate an agreement for professional engineering services to provide design of maintenance repair options to Memorial Drive and Campbell Road within Precinct 3. The total lengths of the projects are 1.7 miles and 1.5 miles, covering the subject roads.

Expected Impact:
The maintenance project will improve the road quality for the community in the specified area.

Alternative Options:
Without this project the road cannot be maintained properly. The goal is to provide better mobility and/or eliminate hazards from the roadway as requested by the Precinct.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and ...