Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 23/0263, UPIN 2110330208023
Vendor/Entity Legal Name (if applicable): Earth Builders LP
MWBE Contracted Goal (if applicable): 29%
MWBE Current Participation (if applicable): 30.55%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Earth Builders LP, in connection with John Paul Landing, North Basin Cell, Phase 3, adding 59 calendar days, with no change in the amount, Job No. 23/0263-2, UPIN 2110330208023, Precinct 4, MWBE Contracted Goal: 29%, MWBE Current Participation: 30.55%.
end
Background and Discussion:
The project involves constructing the third and final phase of the John Paul Landing Detention Basin master plan. Its goal is to provide a stormwater quality detention pond, achieving the full intended functionality of the basin to enhance drainage and reduce flooding risks. Additionally, it offers opportunities for natural and man-made amenities, including habitat creation, recreational trails, and future community programming. The project is located on the eastern edge of the North Basin Cell and runs north-south alongside Langham Creek.
The change involves a 59-calendar-day extension to the contract. The additional time is necessary to complete the final excavation and grading associated with the increased excavation quantities previously added to the contract on Agenda Date: 10.29.24 (Agenda #40 (24-6553)) due to a shortage in the contract excavation quantit...