Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 4
Secondary Department Head/Elected Official: Lesley Briones
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 22/0230, UPIN 23104MF2PP01
Vendor/Entity Legal Name (if applicable): MC2 Civil, LLC
MWBE Contracted Goal (if applicable): 32%
MWBE Current Participation (if applicable): 35.45%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with MC2 Civil, LLC, in connection with final construction of Intersection Improvement - Katy Hockley Road at Clay Road - 2022, adding 259 calendar days, with no change in the amount, Job No. 22/0230-3, UPIN 23104MF2PP01, Precinct 4, MWBE Contracted Goal: 32%, MWBE Current Participation: 35.45%.
end
Background and Discussion:
This project is for the asphalt paving improvements and roadway widening at Clay and Katy Hockley - Harris County Precinct 4.
The change involves a 259-calendar-day extension in contract time. The additional time is necessary to complete the project due to prolonged delays caused by conflicts with existing Kinder Morgan pipelines.
Added Items:
* PCO #4 - Time extension, adding 259 calendar days to the contract.
The project was completed to improve and provide reliable and safe route of transportation to residents of Harris County.
Expected Impact:
The proposed final change order allows an extension of the contract duration, compensation for the contractor's work, and the return of unused funds to the precinct.
Alternative Options:
There are no alternative options or contractor will be dela...