File #: 25-0939    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/25/2025 In control: Commissioners Court
On agenda: 2/6/2025 Final action: 2/6/2025
Title: Request for approval of a change in contract with J Rivas Construction, LLC., in connection with On-Call - Maintenance - Drainage Improvements, South Zone, Precinct 2 - 2021, with no change in the amount, Job No. 21/0286-1, UPIN 22102MF2BQ01, Precinct 2, MWBE Contracted Goal: 14%, MWBE Current Participation: 100%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 2
Secondary Department Head/Elected Official: Adrian Garcia

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 21/0286, UPIN 22102MF2BQ01
Vendor/Entity Legal Name (if applicable): J Rivas Construction, LLC.

MWBE Contracted Goal (if applicable): 14%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with J Rivas Construction, LLC., in connection with On-Call - Maintenance - Drainage Improvements, South Zone, Precinct 2 - 2021, with no change in the amount, Job No. 21/0286-1, UPIN 22102MF2BQ01, Precinct 2, MWBE Contracted Goal: 14%, MWBE Current Participation: 100%.
end

Background and Discussion:
Project includes Drainage Service, Maintenance, and Improvements at Various Locations in the South Zone of Harris County Precinct 2. The Precinct has requested for the new bid items be added to current bid items.

Change includes adding bid Item# 88, item# 89, Item# 90, Item# 91, item# 92 missing in original bid items.
1- Item 88 - 9' x 12' SPEED CUSHION (1) EA- $7,349.49/EA
2- Item 89 - 12-FOOT PARABOLIC SPEED HUMP - $6,469.66/EA.
3- Item 90 - 22-FOOT SPEED TABLE (1) EA - $6,656.66/EA
4- Item 91 - 22-FOOT RAISED CROSSWALK (1) EA - $7,760.08
5- Item 92 - Pipeline Corridor Utility Conflict Inspection Service Fee - $7,500/Day

The new bid item is only to establish the unit price and there is no change to the contract amount.

Expected Impact:
Change allows the contractor to complete drainage improvement within the Pr...