Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official:
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): 15104MF0DN02
Vendor/Entity Legal Name (if applicable): North Harris County Regional Water Authority
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with North Harris County Regional Water Authority in the amount of $62,530 in connection with the construction of water main improvements to Telge Road from 1,650-ft North of Louetta Road to 1,780-ft North of Telge Ranch Road, UPIN 15104MF0DN02, Precinct 3.
end
Background and Discussion:
Harris County desires to include a 16 inch connection to the North Harris County Regional Water Authority water main in the construction plans for the Telge Road from 1,650-ft North of Louetta Road to 1,780-ft North of Telge Ranch Road project. Including this water main connection will ensure that the North Harris County Regional Water Authority will not have to remove the pavement and storm drain that is part of the current construction of the ongoing roadway expansion project. Upon construction completion and acceptance, the North Harris County Regional Water Authority will own and operate the water system.
Expected Impact:
The expected impact of this action is to more efficiently coordinate with area development and utility partners in order to reduce costs and disruption.
Alternative Options:
An alternative would be to have North Harris County Regional Water Authorit...
Click here for full text