Title: Request for approval of a change in contract with Environmental Allies, Inc., in connection with final construction of Sandpiper Village Subdivision Drainage Improvements - 2018, adding 22 calendar days, with a deduction in the amount of $406,831.17, Job No. 22/0457-1, UPIN 19104MF14R01, Precinct 3, MWBE Contracted Goal: 24%, MWBE Current Participation: 32.95%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 19104MF14R01; Job No. 22/0457
Vendor/Entity Legal Name (if applicable): Environmental Allies, Inc.

MWBE Contracted Goal (if applicable): 24%
MWBE Current Participation (if applicable): 32.95%
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Environmental Allies, Inc., in connection with final construction of Sandpiper Village Subdivision Drainage Improvements - 2018, adding 22 calendar days, with a deduction in the amount of $406,831.17, Job No. 22/0457-1, UPIN 19104MF14R01, Precinct 3, MWBE Contracted Goal: 24%, MWBE Current Participation: 32.95%.
end

Background and Discussion:

The Sandpiper Village Subdivision is located northeast of the intersection of Aldine Westfield Road and Treaschwig Road. The scope and proposed improvements include addition of the storm sewers parallel to existing storm along Whitaker Way, upgrade and upsize storm sewer along Donalbain Dr., construction of new detention pond and upsize outfalls into the channel.

The change in contract includes the following:

Quantity Adjustment: The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.

* The increase of quantities on overrun line item numbers 004, 012, 013, 022, 025, 037, 039, 045, 046, 047, 051, and 066 for an addition in the amount of $68,353.95.

* The decrease of quantities on underrun line item numbers 006, 007, 009, 01...