Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 21/0059, UPIN 17102MF0MV01
Vendor/Entity Legal Name (if applicable): SER Construction Partners, LLC
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with SER Construction Partners, LLC, in connection with final construction of Crosby Lynchburg Road Phase 3, with a deduction in the amount of $455,067.28, Job No. 21/0059-11, UPIN 17102MF0MV01, Precincts 2 & 3, Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end
Background and Discussion:
Project includes the reconstruction of approximately 1.85 miles of Crosby Lynchburg Road (FM 2100) from Magnolia Drive south to Lochness Drive and includes the widening of the bridge over HCFCD Channel G103-05. This change in contract includes the final reconciliation of actual quantities used in construction against the bid quantities. Total = (-$455,067.28)
Expected Impact:
This action allows for unused funds to be returned to Harris County.
Alternative Options:
Action required to return unused funds.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all using the county's transportation network in alignme...