Legislation Details

File #: 25-0708    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 1/21/2025 In control: Commissioners Court
On agenda: 2/6/2025 Final action: 2/6/2025
Title: Request for approval of an agreement with Gannett Fleming, Inc. (formerly DE Corp.), in the amount of $438,145, for engineering services in support of the Fondren Diversion Channel project (Brays Bayou Watershed, Bond ID F-08, Project ID D140-00-00-E003, Agreement No. 2024-27, Precincts 1 and 4, MWBE Contracted Goal: 19.625%, MWBE Current Participation: 4%).
Attachments: 1. 020625 AGMT GANNETT 2024-27 PCT 1 AND 4 backup.pdf
Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): D140-00-00-E003
Vendor/Entity Legal Name (if applicable): Gannett Fleming, Inc.

MWBE Contracted Goal (if applicable): 19.625%
MWBE Current Participation (if applicable): 4%
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an agreement with Gannett Fleming, Inc. (formerly DE Corp.), in the amount of $438,145, for engineering services in support of the Fondren Diversion Channel project (Brays Bayou Watershed, Bond ID F-08, Project ID D140-00-00-E003, Agreement No. 2024-27, Precincts 1 and 4, MWBE Contracted Goal: 19.625%, MWBE Current Participation: 4%).
end

Background and Discussion:
This Agreement is for the consultant to prepare a technical memo regarding potential detention basin sites for flood risk reduction along the D140-04-00 channel and surrounding overbank area within Brays Bayou Watershed.

Expected Impact:
The project seeks to reduce flood risks and strengthen resiliency in the Brays Bayou watershed by mitigating the flooding issues in the D140-04-00 channel and surrounding overbank area.

Alternative Options:
The alternative to approving this item would be to not continue with the memo, which would result in flood risk remaining the same.

County Strategic Plan Goal: 5. Minimize the impact of climate change and disasters.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): ...