Legislation Details

File #: 25-0628    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/12/2025 In control: Commissioners Court
On agenda: 1/23/2025 Final action: 1/23/2025
Title: Request for approval of a change in contract with Reliance Construction Services, L.P., in connection with Beaumont Place Phase II Subdivision Drainage Improvements, with an addition in the amount of $785,625.00, Job No. 23/0178-2, UPIN 23208MF2TN01, Precinct 2, MWBE Contracted Goal: 24%, MWBE Current Participation: 100%.
Sponsors: Mony Hossain
Department: County Engineer
Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN - 23208MF2TN01 - Job No. 23/0178
Vendor/Entity Legal Name (if applicable): Reliance Construction Services, L.P.

MWDBE Contracted Goal (if applicable): 24%
MWDBE Current Participation (if applicable): 100%
Justification for 0% MWDBE Participation Goal: N/A - Goal is not 0% and is listed above

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Reliance Construction Services, L.P., in connection with Beaumont Place Phase II Subdivision Drainage Improvements, with an addition in the amount of $785,625.00, Job No. 23/0178-2, UPIN 23208MF2TN01, Precinct 2, MWBE Contracted Goal: 24%, MWBE Current Participation: 100%.
end

Background and Discussion:
The Beaumont Place Subdivision is located in the Greens Bayou watershed near Highway 90 and Beltway 8. The proposed improvements include roadside ditch regrading, driveway culvert upgrades, expansion of channel along Big Gulch, concrete lined Sulphur Gully channel with reinforced concrete box (RCB) crossing improvements. Improvements also include multiple detention ponds along Big Gulch with an extreme event overflow swale towards the upstream portion of the channel.

The change in contract includes the following:

New Line Items: Adding new line items on the project for completion of the proposed scope of work.

* Line item number 203, 2-inch PVC C900 (DR-18), Complete in Place
* Line item number 204, 3-inch PVC C900 (DR-18), Complete in Place
* Line item number 205, 4-inch PVC C900 (DR-18), Complete in Place
* Line item number 206, 6-inch PVC C900 (DR-18), Complete in Place
* Line Item number 207, 8-inch PVC C900 (DR-18), Complete in Place
* Line Item number 208, Furnish and Install 3-inch AWWA Gate Valve with Box per City of Houston Requi...

Click here for full text