Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Transmittal
Project ID (if applicable): Job No. 22/0201, UPIN 19103MF15V01
Vendor/Entity Legal Name (if applicable): R Construction Civil, LLC dba R Construction Company
MWBE Contracted Goal (if applicable): 22.31%
MWBE Current Participation (if applicable): 28.48%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Transmittal by the Office of the County Engineer of a substantial completion certificate with R Construction Civil, LLC dba R Construction Company, in connection with Cimarron Secs 2, 3, 4, and 5 Subdivision Drainage Improvements - 2018, Job No. 22/0201, UPIN 19103MF15V01, Precinct 4, MWBE Contracted Goal: 22.31%, MWBE Current Participation: 28.48%.
end
Background and Discussion:
The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer. Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset. The establishment and reporting of this date are important for all governmental entities as outlined in the GASB Statement #34, Capital Assets & Depreciation Guidance, August 31, 2001. These certificates provide a method by which Harris County may document and record this date.
Expected Impact:
No alternative options.
Alternative Options:
No alternative options.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably d...