Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): P130-02-00-X017
Vendor/Entity Legal Name (if applicable): Solid Bridge Construction LLC
MWBE Contracted Goal (if applicable): 31%
MWBE Current Participation (if applicable): 28.194%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 3 with Solid Bridge Construction, LLC, for Channel Repair along P130-02-00, adding 182 calendar days and resulting in an addition of $69,412 to the contract amount (Greens Bayou Watershed, Bond ID Z-02, Project ID P130-02-00-X017, Job No. 23/0176, Precinct 3, MWBE Contracted Goal: 31%, MWBE Current Participation: 28.194%).
end
Background and Discussion:
This project aims to complete channel repairs along P130-02-00. A contract modification is required to finalize the construction, addressing the need for additional materials to repair a slope failure. This change will add $69,412 to the contract and extend the timeline by 182 calendar days to accommodate the necessary work.
Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits.
Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order other than cancelling the contract which is not recommended as doing so would substantially delay the remaining work in the construction contract.
County Strategic Plan Goal: 2. Connect our community with safe, ...
Click here for full text