Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): K100-00-00-G002
Vendor/Entity Legal Name (if applicable): Midtown Engineers, LLC
MWBE Contracted Goal (if applicable): 19%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with Midtown Engineers, LLC, in the amount of $428,473, to provide additional design, bidding, and construction phase engineering services in support of two detention basins along Cypress Creek at Kuykendahl Road and IH-45, HCFCD Unit K500-31-00 (Cypress Creek Watershed, Bond ID CI-012, Project ID K100-00-00-G002, Agreement No. 2020-09, Precincts 1 and 3, MWBE Contracted Goal: 19%).
end
Background and Discussion:
This Amendment No. 2 will provide additional design, bidding, and construction phase services (CPS) in support Cypress Creek Batch 5 stormwater detention basin and channel maintenance projects. This agreement provides engineering support to the major Cypress Creek channel maintenance repairs, which were separated into five (5) Batch packages under the Bond Program.
Expected Impact:
This amendment will allow the Flood Control District to provide professional engineering and related services as may be needed for this project located within Harris County, Texas.
Alternative Options:
The alternative to approving this item would be procuring another consultant to complete the work, which would result in design and construction delays in the CDBG projects an...