Legislation Details

File #: 25-0366    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/27/2024 In control: Commissioners Court
On agenda: 1/9/2025 Final action: 1/9/2025
Title: Request for approval of a change in contract with Precise Services, Inc., in connection with Crosby Township/MUD Drainage Improvements - 2018, adding 99 calendar days, with no change in the amount, Job No. 23/0438-2, UPIN 19102MF12Q01, Precinct 3, MWBE Contracted Goal: 24%, MWBE Current Participation: 100%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 19102MF12Q01; Job No: 23/0438
Vendor/Entity Legal Name (if applicable): Precise Services, Inc

MWBE Contracted Goal (if applicable): 24%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: Choose an item.

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Precise Services, Inc., in connection with Crosby Township/MUD Drainage Improvements - 2018, adding 99 calendar days, with no change in the amount, Job No. 23/0438-2, UPIN 19102MF12Q01, Precinct 3, MWBE Contracted Goal: 24%, MWBE Current Participation: 100%.
end

Background and Discussion:
This project is located in northeast Harris County in the Jackson Bayou watershed. It is to the west of Beaumont Highway and North of Runneburg Road. The existing conditions of the Runneburg Estates are roadside ditches that ultimately drains into HCFCD channel R100-00-00. The proposed improvements are to regrade roadside ditches, construct a new outfall, and a new detention basin for the Runneburg Estates Subdivision

The Change in contract is needed to reconcile the overrunning items with the underrunning items and adding new line items to the contract. Below is a summary of changes:

Quantity Adjustment: The items are adjusted to reconcile overrun and underrun quantities on the project. The increase of quantities on items (items 5, 10, 18, 24, & 38) for an addition in the amount of $40,364.30 and 92
days. The decrease of quantities on underrun line items (Items 4, 14, 16, 20, 25, 48,...