Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 24103MF3C501
Vendor/Entity Legal Name (if applicable): Neel-Schaffer, Inc.
MWBE Contracted Goal (if applicable): 19.95%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Neel-Schaffer, Inc. in the amount of $143,005.18 for Construction Phase Services in connection with Mound Road Extension- SEGMENT 2, UPIN 24103MF3C501, Precinct 3, MWBE Contracted Goal: 19.95%.
end
Background and Discussion:
This project extends Mound Road 0.86 miles east of Greenhouse Road to Cypress Drive. The project starts with a 41 foot wide concrete pavement section that connects to a separate project (Segment 1). The pavement section will then transition to a 24 foot wide asphalt pavement section. Pavement will end in a cul-de-sac. The existing railroad crossing at Cypress Drive will be closed at the completion of the project. The project is approximately 2,000 feet in length. Drainage will be a combination of swales and subsurface drainage. A detention pond will be constructed that outfalls into Cypress Creek. An outfall will be constructed at Cypress Creek.
Expected Impact:
The new roadway segment will ensure reliable and safe route of transportation to businesses and residents of the Harris County.
Alternative Options:
If no action is taken, the engineer of record will not be accessible for support through the construction of the project.
County Strateg...
Click here for full text