Primary Department: Housing and Community Development
Primary Department Head/Elected Official: Thao Costis, Executive Director
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): D2017-087
Vendor/Entity Legal Name (if applicable): NHPF Temenos Conduit LLC; Temenos Permanent Affordable LL
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Rate is not 0% and is listed above.
Request Summary (Agenda Caption):
title
Request for approval of a sixth amendment to an agreement with NHPF Temenos Conduit, LLC and Temenos Permanent Affordable, LLC for the Temenos IV project to reallocate budget line-items in order to align the budget with the real costs of the project without affecting the overall project budget of $10,881,905.
end
Background and Discussion:
On June 29, 2021, Commissioner's Court approved an agreement between Harris County, NHPF Temenos Conduit LLC, and Temenos Permanent Affordable LLC for the Temenos IV project.
On November 15, 2022, Commissioner's Court approved the First Amendment to the said agreement to extend the 18-month construction completion requirement for an additional four (4) months to June 30, 2023 due to unanticipated rain/hurricane delays, and unexpected infrastructure delays.
On January 31, 2023, Commissioner's Court approved the Second Amendment to the agreement to include budget revisions to various funding sources for the project. Changes to the Harris County CDBG-DR FY17 budget reflect redistribution of funding between the line items; however, the total amount of Harris County's commitment of $11,000,000, remains unchanged.
O...
Click here for full text